The Parks and Recreation Committee met 04/08/2024. They had one action item on the agenda which was the approve a contract for $95,000 to install playground equipment in Highview Park. This item only took a couple minutes to approve, but I have still included a transcript of the discussion such as it was.
The city had originally budgeted $150,000 for the project, so the committee members were very happy to see it come in at only $95,000. Director of Parks, Recreation, and Facilities Dean Gazza said that when seeking designs for this project, they received responses from all 7 of the companies that they reached out to as opposed to only 2 or 3 which was more common.
After reviewing the proposals, city staff went with a design from Lee Recreation, a company that they have used several times before.
View full meeting details and video here: https://cityofappleton.legistar.com/MeetingDetail.aspx?ID=1167643&GUID=C567678C-50FA-4998-BA79-F620FE51B719