On 01/18/2022 the Common Council received an update on the Library Project which included an overview and concept renderings of the scaled down library project.
The Post Crescent had a nice high-level article about it which hits all the main points. The three glass pavilions have been reduced to one and the overall square footage has been decreased from 107,380 square feet to 90,150 square feet. The geothermal system and the rooftop solar panels will remain.
I’m still in the process of preparing the transcript of the presentation and following discussion, but in the meantime, the PDF of the PowerPoint presentation, which includes multiple concept renderings, is available for download.